A brand new high-voltage transmission line has been accomplished alongside Eyre Peninsula’s east coast, bringing extra dependable energy to houses and companies throughout the area.
The 270km line runs from Cultana to Port Lincoln and is supported by 500 new transmission towers and upgrades to 5 electrical substations.
ElectraNet chief government Simon Emms stated after two years of building and greater than 5 years of planning, the brand new line was operational.
“Eyre Peninsula Link is a significant investment in the region, giving residential and business electricity users a more secure and reliable power supply,” he stated.
“As well as improving supply reliability, the new line future-proofs the region’s high-voltage electricity supply to support growth and renewable energy development.”
Mr Emms stated the brand new hyperlink had been efficiently delivered regardless of difficult climate circumstances and the continuing affect of the COVID-19 pandemic.
It offered for a mean of 200 jobs in the course of the building part, peaking at about 300 in early 2022.
The outdated transmission line was greater than 50 years outdated and wanted substantial funding to interchange worn-out parts to make sure buyer reliability.
The value was largely offset by avoiding alternative works on the present line and annual Port Lincoln generator community assist funds.
ElectraNet stated there can be minimal value affect for patrons.
Source: www.perthnow.com.au